Meet the Young Professionals
Sam Larson, PE
Water Resources Project Engineer, AE2S
With four years of industry experience, Sam specializes in civil and water resources design, hydrologic and hydraulic modeling, and construction resident project representation. Throughout this project, he was responsible for final design efforts, storm sewer design, project specifications, bidding documents, hydraulic modeling, and construction coordination.
Logan Vlasaty, PE
City Engineer, City of Burnsville
Logan brings ten years of experience in public works engineering, design, construction oversight, and contract administration. As the City's project manager, he led capital planning efforts, secured funding, obtained council approvals, and guided overall project execution on behalf of Burnsville residents.
Project Overview: TH13/Cemetery Drainage Improvements
The TH13/Cemetery Drainage Improvements project originated from a citywide resiliency study completed by the City of Burnsville in 2018. The study developed a comprehensive two-dimensional stormwater model and identified areas most vulnerable to flooding throughout the city. Among the top 25 highest-risk locations was the TH13/Cemetery project area.
The need for improvements became even more apparent following a significant rainfall event in 2021, when runoff from the area flooded a nearby business parking lot. The site functioned as a natural low point that collected runoff from a large drainage area, but it lacked adequate stormwater storage and a controlled outlet system. As a result, water either infiltrated or overflowed into adjacent properties, creating flooding concerns and erosion risks.
Preliminary design began in 2022 and included alternatives analysis and detailed hydraulic modeling. The project timeline extended longer than anticipated due to design refinements and efforts to secure funding through the Minnesota Pollution Control Agency's Stormwater Resiliency Grant Program. Those efforts paid off, allowing the City to significantly reduce project costs through grant assistance.
Construction began in the summer of 2025 and was completed that fall. Improvements included:
- Construction of two stormwater ponds
- New storm sewer infrastructure
- Articulated concrete block mats for erosion protection
- Site restoration
- A diversion manhole structure that routes flows based on water volume and storage conditions
A permanent wet pond was designed to provide water quality treatment, while a dry pond attenuates larger storm events before gradually discharging to the existing storm sewer system. Both facilities ultimately connect to an existing 60-inch reinforced concrete storm sewer along the western edge of the site.
Overcoming Challenges
Like many stormwater projects, construction presented unique challenges.
One of the most significant obstacles involved managing temporary stormwater systems throughout construction. The City, AE2S, and contractor worked closely together to continuously monitor site conditions and adapt temporary measures as needed. Frequent communication and collaborative problem-solving were critical to maintaining site stability and protecting downstream properties.
Groundwater also posed a challenge during excavation of the wet pond, which required approximately 20 feet of grading cut. Due to site soil conditions, traditional dewatering methods were not practical. Instead, the team implemented an innovative sump dewatering system consisting of a trench box, slotted basket, washed rock, and filter sock. The system was continuously adjusted throughout construction to effectively control groundwater while minimizing sediment discharge.
Impacting the Community
For both Sam and Logan, the project represents much more than new stormwater infrastructure.
The completed improvements significantly enhance Burnsville's stormwater resiliency while reducing flood and erosion risks for nearby properties and businesses. The project also demonstrates how strategic planning, technical expertise, and successful grant funding can help communities address complex infrastructure challenges in a cost-effective manner.
Reflecting on the project, Sam noted that he is most proud of the team he had the opportunity to learn from throughout both design and construction. Logan highlighted the team's ability to solve a complicated drainage problem while delivering the project under budget through successful grant funding and strong collaboration with the contractor.
Lessons Learned
For Sam, the project has been particularly memorable because it spanned a significant portion of his early career. From initial planning through construction completion, the experience exposed him to new technical challenges, decision-making opportunities, and real-world problem-solving situations.
Logan echoed the importance of adaptability, noting that projects of this scale inevitably encounter unforeseen circumstances. Being prepared to think analytically, communicate effectively, and develop practical solutions proved essential to the project's success. The experience also strengthened professional relationships and expanded his understanding of hydraulics and hydrology.
The Value of APWA Connections
One of the unique aspects of this project is that it was delivered by professionals actively involved in APWA and the Young Professionals network. According to Sam, working alongside fellow APWA members made the experience especially rewarding and highlighted the value of the relationships built through the organization.
Both engineers offered valuable guidance for the next generation of public works professionals:
"Learn and soak up as much information as you can and rely on mentors to help you along the way." – Sam Larson
"Learn to enjoy the work we do. The projects we work on are unique, interesting, and important. Don't lose sight of that perspective when you're trying to solve a difficult problem." – Logan Vlasaty
Beyond Public Works
Outside of work, Sam enjoys searching for the best chicken wings in the Twin Cities with his fiancée and spending time with family and friends. A fun fact: he grew up in Garrison, North Dakota, home to a giant walleye statue named Wally. Interestingly, Garrison, Minnesota has its own Wally statue, and both communities claim the title of "Walleye Capital of the World."
Logan enjoys golfing and spending time with his children. His fun fact? Despite living in Minnesota, he admits that he cannot ice skate.
________________________________________
The TH13/Cemetery Drainage Improvements project showcases the meaningful impact young professionals can have when given opportunities to lead, collaborate, and solve complex infrastructure challenges. Through technical innovation, teamwork, and a commitment to public service, Sam Larson and Logan Vlasaty helped deliver a project that will benefit the Burnsville community for years to come.